Project Profile





Murrin Murrin: Nickel/Cobalt Production Facility



FAST FACTS
CUSTOMER
Murrin Murrin Holdings
LOCATION
Western Australia
PROJECT
Brownfield process control optimisation project.
DATE
03-Jun-2002
PLANT DETAILS
Mining and processing of lateritic ore for the production of up to 45,000tpa of nickel and 3,000tpa of cobalt briquettes.
CONTROL SYSTEM
Yokogawa Centum CS






Project Overview

Dry laterite Nickel-Cobalt Pressure Acid Leach Plant & Refinery. Design rate of 45,000 tonnes per annum (tpa) Nickel and 3,000 tpa Cobalt.

MIPAC Scope

• Maintain and support DCS / PLC / Instrument systems
• Development and trouble-shooting across plant areas.
• Implementation of sequencing, batch and auto control strategies.
• Operator and engineer training
• Process optimisation

Technical Highlights

• High pressure acid leaching
• Natural gas reformer
• H2S sulphide precipitation
• Power generation from steam turbines & gas turbine
• Hydrogen reduction based nickel/cobalt refinery
• Organic based solvent extraction
• Air separation plant
• Oxygen based sulphide leach
• Misc materials and process handling system

Results

• Implementation of process improvement recommendations
• Implementation of advanced sequencing, batch & auto-control strategies

Back to Project Summary | Tell A Friend

Tell a Friend

From:

To:

I found this article on the MIPAC website and I thought you may be interested.
 
Captcha Image
 
|  23-Jun-2010 02:56 PM
Follow MIPAC on Linked in