Mipac and PanAust working together again on Phu Kham Increased Recovery Project

Share Post:

Share on facebook
Share on linkedin
Share on email

The successful upgrade of PanAust’s Phu Kham Copper-Gold Operation in Laos has seen Mipac’s remit expand to work on the Phu Kham Increased Recovery Project (IRP).

The IRP involves an investment of US$45 million in capital and is expected to lift annual copper and gold production by about 5000 tonnes and 7500 ounces respectively, and reduce cash costs by more than five per cent.

The mine is located about 120 kilometres north of the Lao capital, Vientiane, and is 90 per cent owned by PanAust’s Lao-registered company Phu Bia Mining Limited. The remaining 10 per cent is owned by the Government of Laos People’s Democratic Republic.

“Mipac is configuring the existing Yokogawa DCS CS3000 to incorporate the control of a new IsaMILL™, flotation cells, a filter press, associated ancillary drives, and a cleaner bank,” senior systems engineer Mohamed Maksoud says.

“I did the design and configuration for the project and will be based in Laos for at least a month to commission the plant. Mipac always tries to have the same people working on a project from start to finish. It creates efficiencies for the client and is helpful for information management purposes.”

PanAust expects the IRP to be completed in the June quarter of 2013.

“This would be two to three months ahead of the original schedule,” PanAust Executive General Manager project development and operational improvement Dr Fred Hess says.

“PanAust and Mipac have a track record of working as a team to develop solutions. Mohamed should be on site in the next few months and we expect to see an increase in life-of-mine recovery rates for both copper and gold in the near future.”

Subscribe

Enter your details to receive our newsletter

    Register for Webinar

    Simply fill out the below form and we will send you the details of the webinar directly to your email.

      Download TCard Case Study

      Simply fill out the below form and we will email you a copy of the MIM Case Study.

        Request a
        Demonstration

        Simply fill out the below form and we will be in touch to discuss the best time for a demonstration.

          Download E-Learning brochure

          Simply fill out the below form and we will email you a copy of our E-Learning Brochure.

            Download our OT Vision to Delivery brochure

            Simply fill out the below form and we will email you a copy of our Capability Statement.

              Download our Capability Statement

              Simply fill out the below form and we will email you a copy of our Capability Statement.

                Download SMART Tankhouse brochure

                Simply fill out the below form and we will email you a copy of our SMART Tankhouse brochure.

                  Download MPA brochure

                  Simply fill out the below form and we will email you a copy of our MPA brochure.

                    Download ShortMeter™ brochure

                    Simply fill out the below form and we will email you a copy of our ShortMeter™ brochure.

                      Download TCard brochure

                      Simply fill out the below form and we will email you a copy of our TCard brochure.

                        Download Copper Monitor brochure

                        Simply fill out the below form and we will email you a copy of our Copper Monitor brochure.

                          Download Cellview® brochure

                          Simply fill out the below form and we will email you a copy of our Cellview® brochure.