Mipac’s engineers continue to support and optimise First Quantum Kansanshi copper smelter after successful ‘heat up’ in Zambia.

Mipac’s strong engineering team assisted the successful delivery of the 1.2Mtpa ISASMELT™ copper smelter project at the Zambian Kansanshi Mine site in record time.

Mipac’s scope of work involved design, configuration, procurement of 2,700 items and the commissioning of +10,000 I/O’s Siemens SIMATIC PCS7 plant-wide process control system (PWCS).

The PWCS included the following areas: Materials handling, ISASMELT™, Matte Settling Furnace, Pierce Smith Convertors, Anode Furnaces, Oxygen Plant, Acid Plant, Plant Services and Common Areas.

Mipac’s well-engineered and robust design was contributed to;
• Using AVEVA software to significantly lower engineering costs and improve the quality of deliverables
• Collaborating with First Quantum and specialist vendors during the software development phase
• Extensive FAT phase to minimise re-engineering prior to commissioning phase

“Mipac’s smooth commissioning of 5 control rooms and field equipment is attributed using our design engineers, involved throughout the project, to carry out commissioning at site,” says Don Robinson, Mipac Operations Manager.

“Our team were highly praised by First Quantum who requested one of our senior controls engineer to remain on-site to provide optimisation support.”

Philip Pascall, First Quantum’s Chairman and CEO, commented June 25th, 2015
“We are very pleased with the performance of the smelter. The achievement of over 100% of nameplate capacity, in just three months from startup, is unprecedented. It is a credit to the design and project teams and illustrates the strong capabilities of the operations management and staff.”

 

Subscribe

Enter your details to receive our newsletter

    Register for Webinar

    Simply fill out the below form and we will send you the details of the webinar directly to your email.

      Download TCard Case Study

      Simply fill out the below form and we will email you a copy of the MIM Case Study.

        Request a
        Demonstration

        Simply fill out the below form and we will be in touch to discuss the best time for a demonstration.

          Download E-Learning brochure

          Simply fill out the below form and we will email you a copy of our E-Learning Brochure.

            Download our OT Vision to Delivery brochure

            Simply fill out the below form and we will email you a copy of our Capability Statement.

              Download our Capability Statement

              Simply fill out the below form and we will email you a copy of our Capability Statement.

                Download SMART Tankhouse brochure

                Simply fill out the below form and we will email you a copy of our SMART Tankhouse brochure.

                  Download MPA brochure

                  Simply fill out the below form and we will email you a copy of our MPA brochure.

                    Download ShortMeter™ brochure

                    Simply fill out the below form and we will email you a copy of our ShortMeter™ brochure.

                      Download TCard brochure

                      Simply fill out the below form and we will email you a copy of our TCard brochure.

                        Download Copper Monitor brochure

                        Simply fill out the below form and we will email you a copy of our Copper Monitor brochure.

                          Download Cellview® brochure

                          Simply fill out the below form and we will email you a copy of our Cellview® brochure.