Ok Tedi Process Control Improvement Project

Client
OK Tedi
Emplacement
Papua New Guinea
Project
Process Control Improvement
Système de contrôle
ABB 800xA

Aperçu du projet

 

OK Tedi management embarked upon a comprehensive upgrade project to their ageing Bailey INfi90 processing plant controls. They engaged Mipac as the Owner Representative in the Plant Control System upgrade project. 

Portée du projet

 

  • Assisting in the selection of the new control system
  • Management of project design, commissioning and implementation
  • Development of specifications and standards for the networking and control system.
  • Developing conceptual designs of the network and control system to allow vendor (ABB) to design appropriate ABB 800xA system.
  • Management of procurement activities.
  • Managed vendor configuration and FAT activities.
  • Managed installation and commissioning activities on-site for control system cutover.

 

Faits saillants du projet

  • Mipac managed a phased upgrade of the automation system for the whole mill
  • The project involved replacing the existing control system which consisted of Bailey Infi90 with ABB 800xA.
  • The 800xA control system was implemented in Parallel to allow a seamless cutover.

 

Demander un rappel

Nous contacter

Vous avez un projet? Parlons.

sales@mipac.com.au
+61 7 3212 5600
Brisbane, Perth, Vancouver