APA Group

Power Station Control System Upgrade and Engineering Services

Mipac has provided control systems and electrical engineering services to the Diamantina Power Station since 2014. During this period many varied projects have been taken from concept/scoping through design to commissioning, integration and support to develop the power station asset capability.

Road sign pointing to Katherine, Darwin and Mount Isa on red soil beside a black road.

Site overview

Within the Gulf Country region of Queensland’s northwest lies the city of Mount Isa, and near it, APA’s Diamantina Power Station (DPS) a modern, high-efficiency power station that services the power needs of Mount Isa and surrounds. As this region is not connected to the National Electricity Market (NEM) and relies on the Northwest Power System to power both industry and residences, this power station is an extremely important asset to the region. 

Background

Mipac was first engaged by APA DPS in 2014 as an owner’s representative for the installation and commissioning of the power plant. We were involved in the preparation of an AVEVA PI Historian and assisting APA DPS to bridge the gap between the existing control system, delivered by Siemens, and what was required for the operation. Our engagement covered project management, engineering and procuring.   

For close to a decade Mipac has continued to provide control systems and electrical engineering services to the DPS across several varied projects. These included concept/scoping, design, commissioning, integration and support services to develop the power station asset capability. 

Lead Control System Engineering Services

For close to a decade, Mipac engineers have been acting as the lead control systems engineers for APA DPS. During this time, Mipac has worked collaboratively with APA and played a critical role in stabilising the plant and enhancing its capacity. 

Over multiple small-scale projects, Mipac has been helping bring the plant to specification and adding value to the client. This has included:  

Challenges

The Mipac team has overcome numerous challenges over the course of its work with the DPS, including: 

Outcomes

Over the course of this work, Mipac has: 

Results

Increased stability of the plant

  • Load sharing on the generators ensured that these could better cope with variable loads.  
  • Mipac’s work resulted in a consistent operation, minimising operator input and providing additional operational flexibility and stability. 

Decreased maintenance requirements

  • Mipac’s work introduced more documentation and better diagnostics for the control system. It also provided a back-up system for the data collected. As a result of this, maintenance time and required effort decreased, with operators having more time to get on with their work. 
CONTACT US

Got a project? Let's talk.

Simply fill out the below form and we will be in touch to discuss the best time for a demonstration.

Request a
Demonstration

Simply fill out the below form and we will be in touch to discuss the best time for a demonstration.

Simply fill out the below form and we will email you a copy of our TCard brochure.

Simply fill out the below form and we will email you a copy of our MPA product guide.

Simply fill out the below form and we will email you a copy of our SMART Tankhouse brochure.

Download our Capability Statement

Simply fill out the below form and we will email you a copy of our Capability Statement.

[contact-form-7 id="7624"]

Download our OT Vision to Delivery brochure

Simply fill out the below form and we will email you a copy of our Capability Statement.

[contact-form-7 id="7623"]

Simply fill out the below form and we will email you a copy of our E-Learning Brochure.

Request a
Demonstration

Simply fill out the below form and we will be in touch to discuss the best time for a demonstration.

[contact-form-7 id="8762"]

Download TCard Case Study

Simply fill out the below form and we will email you a copy of the MIM Case Study.

[contact-form-7 id="8768"]

Register for Webinar

Simply fill out the below form and we will send you the details of the webinar directly to your email.

[contact-form-7 id="8833"]

Request a
Demonstration

Simply fill out the below form and we will be in touch to discuss the best time for a demonstration.

Request a
Demonstration

Simply fill out the below form and we will be in touch to discuss the best time for a demonstration.

Simply fill out the below form and we will be in touch to discuss the best time for a demonstration.

Simply fill out the below form and we will email you a copy of our TCard™ product guide.

Simply fill out the below form and we will email you a copy of our MPA Logsheets product guide.

Simply fill out the below form and we will email you a copy of our Digital TARP product guide.

Simply fill out the below form and we will email you a copy of our Capability Statement.

Simply fill out the below form and we will email you a copy of our ShortMeter product guide.

Simply fill out the below form and we will email you our Copper Monitor™ product guide.

Simply fill out the below form and we will email you a copy of our SMART Tankhouse product guide.

Simply fill out the below form and we will email you a copy of our Alarm Manager product guide.

Simply fill out the below form and we will be in touch to discuss the best time for a demonstration.

Simply fill out the below form and we will be in touch to discuss the best time for a demonstration.

Simply fill out the below form and we will email you a copy of our Copper Monitor brochure.