Seqwater
TEW Landers Shute Sludge Handling Plant and Centrifuge PLC Upgrade
- Seqwater Landers Shute WTP, QLD
- I/O Count 548
- Schneider M340 PLC, Citect SCADA system
Seqwater project to upgrade the sludge handling system at the Landers Shute WTP, involving decommissioning and replacement of equipment. The control system at site required modification and new PLC for additional equipment.
Project scope
- Provision of new sludge handling remote I/O PLC rack integral to the new MMC
- Full integration of the replacement sludge MCC and proprietary centrifuge control panels into the existing plant PLC and SCADA
- PLC and SCADA programming to fully incorporate the new systems into the existing control solution, including detailed alarm and reporting structure to the new MCS specification
- Participation in HAZOP and CHAZOP workshops
- FAT (factory acceptance testing)
- Reviewing and revising the control functional description document
- SAT, Control System commissioning and operator/maintenance Seqwater staff training
Project highlights
- Cutover was undertaken within the planned/scheduled time with no impact ton Brisbane water production and supply
- All site works carried out met the Seqwater safety requirements with no incidents
- Working with the many stakeholders involved in the project ensured commissioning and cutovers were seamless
Discover more of Mipac's projects
Unplanned maintenance was holding Ok Tedi back. With Mipac and Aspen Mtell, the team lifted plant reliability and performance
Mipac stabilised APA’s Diamantina Power Station, delivering tailored control upgrades that improved reliability, diagnostics, and long-term grid performance.
The smelter’s legacy system risk is gone. Mipac migrated critical control into modern DCS infrastructure, reducing outage threats.
CONTACT US